Because of a lapse in government funding, the information on this website may not be up to date, transactions submitted via the website may not be processed, and the agency may not be able to respond to inquiries until appropriations are enacted. The NIH Clinical Center (the research hospital of NIH) is open. For more details about its operating status, please visit cc.nih.gov. Updates regarding government operating status and resumption of normal operations can be found at opm.gov.

 hasheight=  
Building For All
​​​
Click on icons for more information  
 
Building For All - NIH Campus Construction Projects Map

Building For All - NIH Campus Construction Projects Map
picture
Westernmost Roadway to Lot 41 Closed
The westernmost roadway to Lot 41 closed to free up over 100 parking spaces in Lot 41 by moving construction laydown areas for Building 40A, Utility Tunnel Project, campus lighting upgrades and campus-wide roofing projects.
 
Start: March 17, 2025
End: Unknown
 
picture
Construction of Utility Tunnel
Construction of a major utility tunnel and valve vaults for steam and chilled water. Occasional pedestrian path detours and vehicle lane shifting required from intersection of Wilson Drive/Center Drive north along Center Drive to north end of Building 31C.
 
Start: December 2024
End: December 2027
 
picture
Center Drive Entrance Closure
The closure of a portion of Center Drive and Convent Drive is necessary to enable SRLM construction. Alternate access to buildings along the closed road will be provided.
 
Start: January 9, 2023
Reopen: Summer 2028
 
picture
Lot 4A to Valet
Lot 4A will be converted to valet parking for hospital patients and visitors. While this change happens, visitor parking will be available at a new Lot 18 (south side of campus) or MLP-11.
 
Start: February 2022
End: Spring 2029
 
picture
ACRF Parking Changes: P-1, P-2, P-3
Parking changes to include removal of stack parking. Stack parking to be added at Lot 10-H and MLP-9; ACRF Parking Garage for Building 10 Occupants Only
 
Start: Summer 2022
End: August 2027
 
picture
MLP-9 to Building 10 Staff Only; Stack parking added
MLP-9 is now available only to employees who work in Building 10. Special parking hanger required. Stack parking added. Alternate parking is available in MLP-6, MLP-8 and Lot 10-H and other employee lots.
 
Start: February 22, 2022
End: Permanent
 
picture
Lot 10-H Stack Parking
Lot 10-H will add stack parking to increase occupancy.
 
Status: Completed, Permanent Change
 
picture
Lot 18 Temporary Visitor Lot
Lot 18 is a temporary visitor lot replacing Lot 4A. The lot holds 104 vehicles and is open Monday – Friday, 6am – 9pm. The lot will be serviced by the NIH Campus and Campus Limited shuttle routes.
 
Start: December 2022
End: Spring 2029
 
picture
MLP 12 (General Parking Garage)
MLP 12 will have six parking levels and will accommodate 1,399 cars and also has 10 dedicated motorcycle spaces. MLP 12 is primarily for general parking.
 
Start: December 2025
End: August 2027
 
picture
Medlars Drive Near MLP 12 (Heavy Traffic)
Construction of MLP 12 will result in heavy construction traffic and occasionally require lane closures. Drive with caution and watch for pedestrians. Please follow direction from flaggers.
 
Start: December 2025
End: August 2027
 
 
picture
Temporary Road – South Drive to Building 60/Convent
With a portion of Center Drive closed, this temporary roadway will allow access to Buildings 60 (Cloisters), 61 (Convent) and 65 (Safra Lodge).
 
Start: Summer 2022
End: Summer 2028
 
picture
MLP 8 Construction
To repair degrading concrete parking deck slabs. The project is broken into phases to reduce the number of parking spaces affected at any given time. Nevertheless, up to 266 parking spaces will close during each phase. Individual phases typically take up to 2 months to complete.
 
Start Date: November 2024
End Date: April 2027
 
picture
Surgery, Radiology and Laboratory Medicine (SRLM) addition to Clinical Center
11-story addition of a Surgery, Radiology and Laboratory Medicine (SRLM) wing to the NW side of Building 10.
 
Start: Summer 2022
End: Spring 2029
 
picture
MLP-14 (Patient Parking Garage)
Multi-level parking garage to accommodate patients, guests and hospital staff.
 
Start: January 2021
End: Spring 2029
 
picture
Construction of Building 40A
5-story, 65,000 sq. ft. addition to the Vaccine Research Center (VRC).
 
Start: October 2021
End: Summer 2026
 

 

​​
 

If you live or work in the W​ashington, DC metropolitan area, you k​now traffic is a part of daily life. Upcoming and ongoing road and transit improvement projects near the Bethesda campus will be particularly impactful to the NIH community. This website provides information on construction projects, including timelines, expected impact, and a description of the improvements you can expect. The map above summarizes each of the major projects.

The NIH also has a number of resources to ease the effects of traffic on your daily commute, and this website serves as a one-stop shop to link you to them. From work schedule flexibilities that enable you to adapt your work hours and even work location; to tools that help you plan the best route to work; to commuting alternatives, including van pool, public transit, or biking this website connects you to opportunities to improve your commute. Please explore your options and visit the Contact Us page if you have any questions.

Back to top

​​​​​​
​​​Alternative Transportation Options